Working closely with the architects, Green Electrical were able to deliver this high end and complex lighting and power installation with outstanding results.
The installation was undertaken during the summer holidays with 7 classrooms, corridors, a stairwell, a reception area and toilets are being completed with a new lighting installation. The project lasted for 5 weeks and involved working with other trades and to a tight planned works schedule. Throughout this project, Green Electrical were supplying between 2-4 electricians a day to make sure that all works were completed before the deadline.
Using a mixture of LED technology and T5 light fittings we were able to help The Rosemary Works school to reduce their carbon footprint and become energy efficient.